Long Thanh Airport Service Projects Slip, but Agency Says Dec 24 Opening Deadline Stands
Vietnam's aviation authority wants a Dec. 24 completion deadline for six Long Thanh airport service projects after missing the Aug. 31 target, and says there is no basis for further extensions.

- The Civil Aviation Authority of Vietnam asked the Ministry of Construction to push six projects' deadline from Aug. 31 to Dec. 24.
- Only two of the six are at equipment installation; four have not finished basic construction.
- Dec. 24 is described as the airport's scheduled opening day, with no basis for further extensions.
Six service projects at Long Thanh International Airport will not meet their original deadline, but Vietnam's aviation authority says the Dec. 24 opening date still stands, VnExpress International reports.
What slipped
The Civil Aviation Authority of Vietnam (CAAV) has asked the Ministry of Construction to approve a new completion deadline of Dec. 24 for six projects under Component 4 of the airport's first phase in Dong Nai City. Under contracts amended in June, contractors were due to finish construction by Aug. 31.
Only two projects have reached equipment installation: the No. 2 aviation catering facility and the No. 2 ground handling and vehicle maintenance center. The other four have not finished basic construction: the No. 1 catering facility, the No. 1 ground handling center, and aircraft maintenance facilities No. 1, 3 and 4.
Reasons given
The CAAV cited heavy workloads, shortages of labor and materials, and fluctuating fuel prices. Longer shipping times for specialized imported equipment also hurt the schedule, and unfinished shared technical infrastructure has stopped contractors from setting up work sites, building access roads and connecting utilities. It said Dec. 24 is the final deadline and there is no basis for more extensions before the airport starts operating at midnight.
Background
The airport covers about 5,000 hectares at a cost of VND336.63 trillion (US$13.16 billion). It is meant to relieve Tan Son Nhat Airport, 40 km to the west. The first phase has one runway and a terminal sized for 25 million passengers a year.
For travelers, the report concerns catering, ground handling and maintenance support rather than passenger terminals, and it does not address flight schedules.
Source: VnExpress International.